Wellington Lakes Shoreline Restoration

Project Photos →
Black location icon on white background.

Location:

Wellington in Fort Myers, FL

Black calendar icon on white background.

Install Date:

2020-2022

Black pencil icon on white background.

Engineer:

Hole Montes Engineers

Black leaf icon on white background.

Erosion System:

Organic Shoreline SystemTM, Hybrid Shell SystemTM

Project Details

After two years of waiting on permitting from the county, we proposed that this client allow us to install our Organic Shoreline System on their entire lake. This shoreline remediation plan required no county permit as it is considered “lake maintenance”. The client was thrilled and signed our contract a couple weeks later! We corrected the slope on this 3,000 linear foot lake, installed biodegradable TRM, and planted a littoral shelf. The finished product looks natural, and is working well.